10 january 2014
The Lungmen nuclear power plant could be in operation by the end of this year or early next year, according to reported statements from Taiwanese planners.Technology newspaper Digitimes reported the Ministry of Economic Affairs as saying said a batch of systems tests at Lungmen 1 should be finished by April, with ’full testing’ complete by the end ...
Industry news
08 january 2014
Installation of the containment dome marks a significant milestone in the construction of the second of two reactors being built in Pakistan by Chinese companies.The dome — measuring 36 metres in diameter, 9 metres in height and weighing some 185 tonnes — was emplaced on the top of the containment building of Chashma unit 4 on 2 January. The ...